Click on the mapDivision Avenue and Suquamish Way 
Road and Drainage Improvements
(CRP 1576)

Bid Opening:  May 3, 2011 at 11:00 am - click here for more information

This project encompasses Division Avenue from Columbia Street to Suquamish Way, and Suquamish Way from Division Avenue to Augusta Avenue, in North Kitsap County.

These proposed improvements are the result of combining needs and dollars:

  • Division Avenue was identified within the Suquamish Community plan developed in 2005 as an area to improve pedestrian facilities

  • A drainage study from 1999 identified drainage issues and conveyance requirements within Suquamish.
     
  • Roads in need of maintenance and repair

The Suquamish Citizens Advisory Committee and the Suquamish Elementary School were the catalysts behind an application for a Safe Routes to School Grant, received in 2007. This grant laid the funding foundation for sidewalk improvements within Suquamish. The Federal sidewalk grant combined with dollars from the Storm and Surface Water Utility (SSWM) for drainage improvements, and the Road fund for road improvements, led to three (3) significant improvements within Suquamish. The first completed in 2008, Augusta Avenue (Center to Geneva); the second completed in 2009, Geneva Street (Augusta to Division) and Park Boulevard (Geneva to Prospect); and now the third to be constructed in 2011, Division Avenue and Suquamish Way.

  Planned improvements include:

     Division Avenue (Columbia Street to Suquamish Way)

  • Two twelve foot wide travel lanes

  • A five foot cement concrete sidewalk on the west side of
    the road

  • Landscape swales on the east side of the road

  • Drainage improvements including a large storm sewer and conveyance

  • Replacement of the existing water main by Kitsap Public Utility District (PUD)

     Suquamish Way (Division Avenue to Augusta Avenue)

  • Storm water conveyance

Estimated Project Cost (Road and Storm)                                                                          

Preliminary Engineering for
Road and Storm

$150,000 ($115,000 road fund, $35,000 SSWM fund)
Right of Way

$80,000 (Road Fund)
Construction
$2,150,000 ($78,000 Road fund, $250,000 Federal Grant, $1,822,000 SSWM Fund)

TOTAL:

$2,380,000
 
 
Demographics                                                                                                                      
County Road Number 71991
             Division Street in Suquamish
Beginning Milepost:  .64
Ending Milepost:  1.03
Total Mileage for this project:  .39
Bicycle Facilities Ranking: Opportunity
Traffic count on Division Avenue (2009): 3,352

Project Schedule and Status                                                                                                  

  Preliminary Engineering Start End
       Road and Storm Conveyance
2009 Completed March 2011
       Water Main (KPUD)
Fall 2010 Completed Dec. 2011
       Right of Way
2010 Completed March 2011
   Construction    
        Road and Storm Conveyance
Spring 2011 End of 2011
               Bid Opening
May 3, 2011  
               Public Open House June 8, 2011  
               Award before the BOCC June 13, 2011  
               Construction Starts June 14, 2011 December 2011
  Water Main (KPUD) Early 2011 Completed March 2011

    Photos and Drawings                                                                                                         

Typical cross-section 

Final Project Plans and Specifications March 31, 2011

Staff contact:   Kristina Nelson PE , Senior Program Manager
                      (360) 337-5777