NW Newberry Hill RoadRestrictedAt the intersection with
Tieton Pl NW

Work on this project is scheduled for two phases. During the summer new sidewalks and the road work is planned. In the fall the contractor will set poles and activate the signal. Work continues through December 2018. See more about this project at the project site online.

Northeast Electric will be installing a new traffic signal as part of County Road Project 3685. Work is scheduled to begin in the beginning of July.
7/2/201812/31/2018Central
Ridgetop Boulevard NWRestrictedBetween
Waaga Way (SR 303) to Quail Run Dr
Moderate delays of 5-10 minutes in the immediate vicinity of the work. Flaggers will direct motorists through the work area.
This phase (Phase 1 of 3) of the project will construct an additional southbound travel lane from Hillsboro Dr to Waaga Way, a 10 ft sidewalk on the east side of the roadway, seven bioretention cells in the medians, two mini-roundabouts and pedestrian safety improvements at the intersections of Marigold Drive NW and Quail Run Drive.
4/23/20182/15/2019Central
Tracyton Blvd NWClosedBetween
For approximately 150 feet between Darling Rd NW and Silver Beach Dr. NW. Detour will be set up along Fairgrounds Rd NW and Stampede Blvd NW.
A contractor is replacing an existing culver here. Read more at the project site online.
Hansen Excavating will be installing a new concrete 3-sided culvert under Tracyton blvd as part of County Road Project 3666. This work is set to begin at the beginning of July.
7/2/201812/31/2018Central
Washington Boulevard NERestrictedBetween
4th St NE and end of maintenence.

10,000 pound weight restriction in place

Road is gravel in places and restricted to one lane. 10,000 pound weight restriction is in effect.

1/1/2017North